RISC-V

Spec Plan Editor

Plan a RISC-V specification's lifecycle, from inception to ratification.

ISA Explorer

Timeline

  • Drag to adjust duration
  • Approval or vote
Phase Activity Start Date End Date Duration (Days)
Inception New Project Committee or Fast-Track Proposal
Proposing a new Task Group? Plan it in the Group Plan Editor
2026-11-18
30
Planning Plan Tasks 2026-11-19 2026-12-18
30
Planning Governing Committee Review (14-day minimum) 2026-12-19 2027-01-01
14
Planning Governing Committee Approval (14-day minimum) 2027-01-02 2027-01-15
14
Development Development Tasks 2027-01-16 2027-03-16
60
Development Project Committee Approval (not required for Fast-Track) 2027-03-17 2027-03-30
14
Development Governing Committee Approval (14-day minimum) 2027-03-31 2027-04-13
14
Stabilization Internal Review (14-day minimum) 2027-04-14 2027-04-27
14
Stabilization Stabilization Tasks 2027-04-28 2027-05-27
30
Stabilization Project Committee Approval (not required for Fast-Track) 2027-05-28 2027-06-10
14
Freezing ARC Freeze Approval 2027-06-11 2027-07-25
45
Freezing RISC-V Compliance 2027-07-26 2027-08-01
7
Freezing Freeze Tasks 2027-08-02 2027-08-16
15
Freezing Governing Committee Approval (14-day minimum) 2027-08-17 2027-08-30
14
Ratification-Ready Public Review (30-day minimum) 2027-08-31 2027-09-29
30
Ratification-Ready Ratification-Ready Tasks 2027-09-30 2027-10-14
15
Ratification-Ready ARC Ratification Approval (if substantial changes after public review) 2027-10-15 2027-10-15
0
Ratification-Ready TSC Approval (14-day minimum) 2027-10-15 2027-10-28
14
Publication BoD Approval 2027-10-29 2027-11-25
1

Plan Summary

Key milestones and target dates